In January of
2006, WDOT awarded Oftedal a two year
contract to reconstruct a 13.5 mile section
of US 287 between Moran Jct. & Dubois, WY.
When complete, Oftedal will have self
performed the excavation and grading of 1.5
million CY of earth, processed over 300,000
tons of crushed base and 170,100 CY of sub
base, installed over 5 miles of pipe
and culvert ranging from double cell 10' x
10' reinforced concrete box culverts to 24"
corrugated metal drain pipe, constructed
four geogrid reinforced fills and repaired
four slide sections situated in steep,
rugged terrain. |
|
|
In October
2006, Oftedal began construction on four
earthen flood control structures designed to
retain or divert storm water from expanding
coal mine operations. By February 2007, over
2 million CY of earth were moved completing
construction of a three mile diversion
channel. |
 |
|
Reconstruction of a five mile section of
I-25 in Converse and Natrona counties
required widening both the north and south
bound lanes, filling median ditches and
recontouring shoulders. Oftedal placed over
900,000 CY of material using scrapers, haul
trucks, and belly dumps. |
 |